Rewiring a two-story 1920s house with plaster walls
Example project

- Home
- 1920s two-story Craftsman house in Shoreline, about 1,900 sq ft, lath and plaster throughout
- Original request
- Replace the knob-and-tube that still feeds most rooms, and keep the original plaster
- Found
- Live knob-and-tube upstairs and in most main-floor rooms; a 1950s kitchen on braided cable with no ground
- Work
- Every old circuit replaced with grounded cable through the attic, the basement and about 30 planned openings
- Timeline
- About three weeks of wiring, the inspection, then patching by a plasterer
- Estimated cost
- $36,500
Scope of work
Each circuit traced, new grounded cable run from the panel through the attic and basement and fished through about 30 planned openings in the plaster, new boxes, outlets, switches and light connections, new circuits for the kitchen counter and bathroom, the old circuits disconnected and the runs that can be reached in the attic and basement pulled out. Permit and inspection are included. Plaster patching and any panel change are priced separately.
Project overview
In this example, a 1920s two-story house in Shoreline still has live knob-and-tube upstairs and in most main-floor rooms, while the kitchen was redone in the 1950s with braided cable that has no ground. The owners want it all replaced, but they want to keep the original plaster.
A two-story plaster house takes more planning than a single-story one, because not every upstairs wall can be reached from the attic and not every downstairs wall from the basement. The scope marks about 30 small openings before anything is cut, mostly at the tops of walls and behind baseboards. They stay open until the L&I inspector has seen the new cable, and then a plasterer closes them.
The goal
The goal is a house on grounded circuits throughout, with the original plaster kept and every opening patched after the inspection.
Process
- Before work A survey of every circuit, the openings marked on a floor plan, and the permit bought.
- Week one Upper floor rewired from the attic, with openings cut only where marked.
- Week two Main floor rewired from the basement, and the kitchen and bathroom put on new circuits.
- Week three Devices fitted, old circuits disconnected and the runs that can be reached pulled out.
- Then Inspection with the openings still open, then a plasterer patches them.
Planning right
- Agree in the quote who patches each opening. Here a plasterer does it after the inspection.
- Baseboards and door casings can often be lifted off and refitted, which hides an opening completely.
- The 1950s kitchen cable has no ground either, so it is part of the rewire rather than left for later.
- Keep the circuit list and permit number. A future buyer’s inspector will ask about the old wiring.